KGJ Price Railway Contractors were contacted by the client outlining a critical failure occurring on the local rail infrastructure.
Faced with a 12-week lead time from their existing supply chain and an inevitable closure of an arterial route into Cardiff city centre, KGJ Price Railway Contractors were able to design, manufacture and be ready to install the replacement in less than ten days.
The key deliverables for this project were as follows: Timely manufacture and delivery. Attendance at planning and integration meetings, on site delivery and installation working under a 36-hour blockade, supply of specialist supervision and PTS operatives to undertake loose lay build up of the unit as well as installation.
100% of materials provided from KGJ Price Railway Contractors stock.
100% of manufactured materials provided in-house at KGJ Price Railway Contractors Manufacturing HUB.
All on site staff provided from KGJ Price Railway Contractors Employed staff.
Project completion in 26 hours of the 36 available.
Successful delivery and reduced risk exposure for our client on a high risk asset. No additional interrupted passenger services.
The works delivered by KGJ Price Railway Contractors Railway Contractors at Cardiff Queen Street, specifically on Points 9452B, were of an exceptionally high standard. Their team demonstrated strong technical expertise and a proactive approach to problem-solving, ensuring the project was completed safely, efficiently, and with minimal disruption to the operational railway.
Their collaborative attitude with both Amey and Transport for Wales stakeholders gave us confidence throughout the programme, and the quality of the finished installation reflects the professionalism and reliability we’ve come to expect from KGJ Price Railway Contractors.
This project is a clear example of how trusted specialist contractors can add real value to the permanent way portfolio.