As part of the new signalling project KGJ Price were appointed sub-contractors to carry out the works below.
- Supply & Installation of 72 nr IBJ’s
- Recover IBJ’s & Install Plain Line Closures – 60 nr
- Plain Lining Turnouts @ Gillingham & Yeovil Stations
- Removal of 2 nr Sidings @ Gillingham & Yeovil
- Installation of Double Slip @ Yeovil Station
- Supply & Installation of New Timbers as Part of Point Conversion
- All works carried out in Possessions
- Average length of possession 5 hours – 4 Rails Inserted per Possession
- S&C Works average 30 hour possessions
- Works Commenced September 2011 – May 2012