Salisbury – Exeter Re-signalling

Salisbury – Exeter Re-signalling Project

As part of the new signalling project KGJ Price were appointed sub-contractors to carry out the works below.

  • Supply & Installation of 72 nr IBJ’s
  • Recover IBJ’s & Install Plain Line Closures – 60 nr
  • Plain Lining Turnouts @ Gillingham & Yeovil Stations
  • Removal of 2 nr Sidings @ Gillingham & Yeovil
  • Installation of Double Slip @ Yeovil Station
  • Supply & Installation of New Timbers as Part of Point Conversion
  • All works carried out in Possessions
  • Average length of possession 5 hours – 4 Rails Inserted per Possession
  • S&C Works average 30 hour possessions
  • Works Commenced September 2011  – May 2012