Bodmin & Wenford Railway

BODMIN & WENFORD RAILWAY

Following flash flooding late 2010 KGJ Price were appointed main contractors to repair 800m of single line track.

  • The works involved removal of the existing track.
  • Removal of approx. 300mm of bottom ballast
  • Repairs / strengthening of the damaged formation
  • Installation of new bottom ballast
  • Relaying track
  • Renovation work to existing track side drainage
  • Installtion of approx. 100m track side fencing
  • The works were completed within a four week blockade in March 2011